Long Duration Jobs

In general the assumption is that jobs booked into the system will have some duration less that the available shift time on a single day for any given operative. Where jobs require duration larger than this they will be split up (fragmented) into a number of parts, over multiple days/shifts, and are booked as a set of dependent jobs. Only certain jobs types may be booked in this way – these must be pre-defined.

...